Spl. High Court Appeals
No.159,
160, 161 and 162 of 2001.
& MR. JUSTICE MUSHEER ALAM.________
Dates of hearing: 15.08.2001,
21.08.2001, 28.08.2001,
29.08.2001, 30.08.2001 & 4.9.2001.
Mr.
Syed Sharifud-din-Pirzada, the learned counsel
for the appellants.
Mr.
Khalid Anwar, the learned counsel for the respondent.
The facts
as stated by the appellants in the memos of appeals are that the respondent
in 1982 granted several loan/ finance facilities to the tune of Rs.584,065,920/-
to M/s Dadabhoy Cement Industries Limited (hereinafter referred to as
DCIL) to make payment of a total sum of Rs.1,013,066,026/- towards the
repayment of the above loan facility. The above loan facilities were
secured by way of mortgage of the properties of DCIL and after making
payment of the aforesaid amount, DCIL filed a suit against the respondent
for redemption of mortgage being suit No.416/96, whereas the respondent
filed a suit against DCIL being suit No.1430/97 for recovery of the
amount allegedly outstanding in respect of the aforesaid loan facilities.
In suit No.416/96, the parties filed an application under Order XXIII
Rule 3 CPC (hereinafter referred to as the Compromise) for disposal
of the suit in terms of the compromise. As the appellants have vehemently
challenged the legality and propriety of the Compromise and had prayed
for its cancellation, it will be appropriate to reproduce the same in
extenso as under:-
It is submitted on behalf of the
parties in the above suit that pursuant to a Memorandum of Understanding
dated 19.12.1997 (Annexure ‘A’) executed between Dadabhoy Cement Industries
(“DCIL”) the Plaintiff No.1 herein and NDFC the Defendant a settlement
has been arrived at including the dispute in the present suit encompassing
all the disputes in relation to the accounting of various facilities
provided by NDFC to DCIL and rescheduling/ restructuring
of there loans/ facilities including the dispute in the present
suit. The dispute involved in the present suit has been resolved on
the following terms and conditions:-
1.
That
it has been agreed between the parties that the interest based loan
facilities and mark up based finance facilities specified in Annexure
‘B’ offered by NDFC to DCIL shall be treated as withdrawn/ cancelled
in all respect as if the said facilities as to each and every one of
them was never offered by NDFC to DCIL.
2.
That
it has been agreed between the parties that out of the amounts from
time to time paid by or for the account of DCIL to NDFC and received
by NDFC upto 1.9.1997 on account of various interest based term loan
facilities as well as mark up based term finance facilities, an aggregate
amount of Rs.948.10 million (Rupees Nine Hundred Forty Eight million
one Hundred Thousand only) received from DCIL (in cash, through adjustment
of certain loan amounts disbursements, amounts reimbursed by the local
banks and Rs.10.36 million received from Asian Development Bank) shall
be deemed to have been received and appropriated by NDFC in part payments
of amounts owing from DCIL on account of the interest based term loan
facilities and in payment of the mark up based term finance facilities
provided to DCIL.
3.
That
on the basis of the appropriation as stated in para 2 thereof, the account
of interest based term loan facilities shall be deemed to be re-stated,
resulting in an aggregate amount of Rs.717,000,000.00 (Rupees Seven
Hundred Seventeen Million only) owing and payable in respect of the
aforesaid facilities which shall be paid by DCIL to NDFC in the manner
stated hereafter.
4.
That
it is further agreed between the parties that the mark up based term
finance facilities (with the exception of working capital facilities
which is subject mater in suit No.1430/97 and for which a separate compromise
Application has been moved) shall be deemed to have been settled and
finally closed for all intent and purposes.
5.
That
as a result of the settlement so arrived at between the parties DCIL
is liable to pay to NDFC an aggregate amount of Rs.717,000,000/- as
on the effective date i.e. 1.9.1997 which DCIL has agreed to pay to
NDFC in the following manner.
6.
That
on execution of the aforesaid memorandum of understanding dated 19.12.1997
DCIL has paid to NDFC the sum of Rs. Two (2) million and the balance
of Rs.715,000,000 (Rupees seven hundred fifteen million only)) payable
on account of interest based term loan facilities shall, from the effective
date i.e. 1.9.1997, bear interest @ 15% per annum on daily balance and
on the basis of a 360 days year with quarterly rest until full payment
of principal and interest is made to NDFC. The aforesaid sum of Rs.715,000,000/-
shall be payable by DCIL to NDFC within 15 years from the effective
date i.e. 1.9.1997 in 60 (sixty) equal quarterly installments payable
on or before 1st January, 1st April, 1st
July and 1st December in each calendar year together with
interest accrued at the rate aforesaid upto the date of payment of each
such installment as detailed in Annexure ‘C’ with the fist such installment
shall be payable on or before 1.4.1998.
7.
That
in the event of default in payment of any installment, as agreed upon
the entire principal and interest accrued thereon then remaining unpaid,
shall become immediately due and payable by DCIL to NDFC without any
notice. In such an event DCIL shall be liable to pay to NDFC an additional
interest @ 4% per annum with semi annual rest on the entire amount of
overdue principal, and interest in addition to the 15% interest per
annum on daily balances, as stated in para 6 hereof.
8.
That
it is agreed that the following shall constitute an even of default:
i.
If DCIL shall
default in making any payment due to NDFC or shall be in breach of any
provision of the said MOU dated 19.12.1997 or of any agreement, as modified
by the said MOU, governing any interest based term loan facility or
of any compromise decree of this Hon’ble Court or of any document creating
or evidencing security in favour of NDFC whether alone or together with
others for money owing from DCIL to NDFC.
ii.
If DCIL shall
suffer any petition for its winding up to be filed or any resolution
for its winding up to be passed or any decree for money to be passed
or any receiver or administrator or manager to be appointed in respect
of the business of DCIL or any of its assets on income in or over which
NDFC has a security interest.
iii.
If in the opinion
of NDFC any security held by it for the indebtedness of DCIL is adversely
affected, whether on account of actions taken or threatened by one or
more creditors against the assets of DCIL in or over which NDFC has
a security interest for money owing from DCIL.
iv.
If DCIL fails
to fulfil any one or more of its obligations including the disposal
of the various cases filed by DCIL and NDFC against each other pending
in this Honourable Court in pursuance of the settlement arrived at through
the aforesaid memorandum of understanding.
9.
That
it is clarified and fully understood by the parties that notwithstanding
the execution of the aforesaid MOU, al the credit agreements and security
documents executed by DCIL in favour of NDFC and personal guarantees
given by the Plaintiff No.2 to 7 shall remain valid binding and enforceable.
However, the terms and conditions of the credit agreements, security
documents including personal guarantees shall be deemed to have been
modified pursuant to the execution of the aforesaid MOU.
It is, therefore, prayed that this
Honourable Court may be pleased to dispose of the above suit in terms
of compromise as stated herein above with no order as to costs.
The Compromise was allowed vide order dated 18.2.98 and it
will also be useful to reproduce the order as under:-
18.2.1998.
Mr. Arshad Mohsin alongwith Nayyar Karim Company
Secretary of the Plaintiff.
Mr.
Afsar Abidi, Advocate
for defendants.
The parties have jointly
filed application under Order XXIII Rule 3 CPC, seeking disposal of
the suit in terms of the compromise recorded therein. The application
is signed by all the plaintiffs and their learned counsel. On behalf
of the defendants one Talat Behzad and the learned counsel
for the defendants have signed the application. The signatures are duly
verified by the learned counsel who admit execution of the application
by their respective clients. I have examined the terms of the compromise
which appear to be lawful and within the scope of the suit with the
exception that in para-7 of the application, the plaintiff have burdened
with liability to pay to the defendant additional interest at the rate
of 4% per annum with bi-annual rests on the entire amount of over-due
principal and the interest. The last mentioned term amounts to imposition
to penal interest which cannot be allowed. In the circumstances, such
term is modified and it is ordered that para-7 of the application shall
be incorporated in the decree as follows:-
“7. That in the event of default in payment
of any installment, as agreed upon, the entire principal and interest
accrued thereon then remaining unpaid, shall become immediately due
and payable by DCIL to NDFC without further notice. In such an event,
NDFC shall be entitled to file execution application seeking payment
of the entire amount as above from the plaintiffs.”
With the above modification, the application is granted and
the suit is decreed accordingly with no order as to costs.
Sd/-
J U D G E
Suit No.1430/97 filed by respondent
NDFC was also disposed of in terms of the above compromise and consent
order.
According to the above
Compromise and the order dated 18.2.98, DCIL had undertaken to repay
a sum of Rs.715,000,000/- together with interest at 15 per cent per
annum on daily balance with quarterly rest. This amount was to be repaid
within fifteen (15) years effective from 1.9.97 in sixty (60) equal
quarterly instalments payable on or before 1st January, 1st
April, 1st July and 1st December and first such
instalment was payable on 1.4.98. According to paragraph 7 of the Compromise,
on default in payment of any instalment on the part of DCIL, they would
become liable for payment to NDFC of the entire principal amount and
the interest accrued thereon immediately without any notice. DCIL defaulted
in the payment of quarterly instalments after making payment of four
(4) quarterly instalments. Thereafter DICL filed applications under
Section 12(2) CPC in June 1998, whereas the respondents filed execution
applications in both the aforesaid suits. Application under Section
12(2) filed in suit No.416/99 was registered as J.M.30/99, whereas such
application in suit No.1430/97 was registered as J.M. 29/99. Both the
aforesaid J.M. petitions and the two Misc. Applications in the two execution
applications being Ex. Applications No.110/2000 and 137/2000 were disposed
of by order dated 18.6.2001, whereby the learned single Judge refused
to recall the order dated 18.2.98 and dismissed both the J.M. petitions
No.29/99 and 30/99. Feeling aggrieved and dissatisfied with the aforesaid
order, the appellants have filed the aforesaid four (4) Spl.
HCAs.
We have heard the arguments of Mr.
Syed Sharif-ud-Pirzada, the learned counsel for the appellants and Mr.
Khalid Anwar, the learned counsel for the respondent. We have also perused
the material on record, the relevant provisions of law and have gone
through the case law relied upon by the learned counsel in support of
their respective arguments.
It was agreed upon by the learned counsel
for the parties that all the four Special High Court Appeals may be
disposed of finally at the stage of Katcha Peshi, if need be after admitting
them to regular hearing.
Mr. Syed Sharif-ud-din Pirzada assailed
the Compromise as well as the order dated 18.2.98 allowing the said
Compromise and disposing of suit No.430/96 in terms of the contents
of the above Compromise on the following grounds:-
(A)
That MOU was based on misrepresentation,
suppression of facts, deliberate and gross miscalculation on the part
of the respondents with the intention to coerce DCIL to make payments
of the amounts in excess of the amounts legally due and payable and
recoverable from DCIL which the respondents were prohibited by Banking
Control Department’s (hereinafter referred to as BCD) circulars No.13
and 32 of State Bank of Pakistan and that the original amount of loan
was blown up by respondent NDFC out of proportion by addition of
interest, penal interest and mark up over mark up which was prohibited
by law in the form of BCD’s circulars No.13 and 32.
B)
That the aforesaid facts not only constituted
commission of fraud as contemplated by Section 12(2) CPC but also amounted
to jurisdictional defect inasmuch as any action in clear disregard of
law cannot be said to be an action or order according to the jurisdiction
vesting in the authority and would amount to unlawful order for want
of jurisdiction as contemplated in Section 12(2) CPC.
C)
That the said order was also defective
and illegal as the learned Single Judge failed to take into consideration
the provisions of Corporate and Industrial Restructuring Corporation
Ordinance, 2000 (hereinafter referred to as CIRC Ordinance L of 2000
LVIII of 2000) which provided an expeditious legal remedy for recovery
of outstanding loan payable to the Bank or financial institution by
a non-performing asset by referring the same to State Bank of Pakistan
for calculation of the actual amount due by the verification Committee.
Mr.
Sharifud-din-Pirzada further submitted that
MOU and the consent decree suffered from misrepresentation as narrated
above and had been obtained by fraud and further that such a consent
decree/ compromise could be set aside on the ground that it was obtained
by fraud if the aggrieved party could establish fraud or illegality.
Further argument of Mr. Sharifud-din- Pirzada was that a consent decree did not stand
on a higher footing or pedestal than an ordinary decree and could be
set aside or recalled if it could be proved that the same was obtained
by practising fraud on the court and/ or was against any express provision
of law in support of this above contention, he placed reliance on the
following cases:-
1.
Zafar Ahmad and 5 others versus Government of Pakistan
through Secretary, Ministry of Production, Islamabad and 6 others (1994
MLD 1612);
2.
Government of Sindh through the Chief Secretary and others
versus Khalil Ahmed and others (1994 SCMR 782) ;
3.
Union Carbide Corporation and others versus Union of
India and others (1991) 4 SCC 584 ; and
4.
State of Punjab (now Haryana)
and others versus Amar Singh and another (1974) 2 SCC 70.
He
further submitted that there was no such principle that a party who
was aggrieved by a consent decree having been obtained by fraud or was
contrary to law was estopped from challenging the consent decree on
the ground that there was no estoppel against law. In support of his
above contention he placed reliance on the following cases:-
1.
Ruby Sales and services (P) Ltd. and another versus State
of Maharashtra and others (1994) 1 SCC 531
;
2.
Pir Sabir Shah
versus Shad Muhammad Khan, Member Provincial Assembly, N.W.F.P. and
another (PLD 1995 SC 66);
3.
Malik Asad Ali and others versus Federation of Pakistan
through Secretary Law, Justice and Parliamentary Affairs Islamabad and
others (PLD 1998 SC 161) ; and
4.
Muhammad Ayub Khan versus The Custodian of Evacuee Property
and others (PLD 1963 Karachi 551).
Another ground on which the impugned order dated
18.6.2991 was assailed was that the application under Section 12(2)
CPC was vigorously contested by the parties inasmuch as counter affidavit
and affidavit-in-rejoinder were filed by the aforesaid parties and in
view of the controverted and disputed issues and questions of facts
and law, it was incumbent upon the learned Single Judge to enter into
an investigation and inquiry and the learned Single Judge in dismissing
the application under Section 12(2) CPC without holding an inquiry and
investigation into the disputed questions of facts and issues committed
an illegality as a result of which his order has been rendered unlawful
and is liable to be set aside. In support of his above contention, he
placed reliance on the following cases:-
1.
Ghulam Muhammad versus M. Ahmad Khan and 6 others (1993
SCMR 662) ;
2.
Abdul Razzaq versus Muhammad
Islam and 3 others (1999 SCMR 1714)
Mr.
Khalid Anwar, the learned counsel for the respondent objected to the
maintainability of the aforesaid appeals and submitted that they were
hopelessly time barred but the appellants by circumvention of law proceeded
to initiate the proceedings, which they were not legally entitled to
initiate, with a view to obtain orders from a court of law which could
provide them fresh period of limitation for filing the aforesaid appeals.
Elaborating his arguments, he submitted that the order dated 18.2.1998
was passed on the Compromise, the contents of which were reduced to
writing with the agreement and consent of both the contesting parties
and both of them had full knowledge and awareness as to the contents
thereof as well as the implication of the contents. In the circumstances,
there was no occasion of the Compromise being based on misrepresentation,
miscalculation and concealment/ suppression of facts or that the order
dated 18.2.98 was obtained by way of fraud as a result of which the
grounds of fraud and misrepresentation mentioned in Section 12(2) CPC
would not be available to the appellants. He further submitted that
mere mention by the aggrieved party that the compromise application
contained statements and figures based on misrepresentation, concealment
of facts and miscalculation was not sufficient to warrant maintainability
of an application under Section 12(2) CPC on the basis of fraud and
misrepresentation and it was necessary for the appellants to have mentioned
in detail the particulars of the misrepresentation, concealment of facts
and miscalculation of the figures. In support of his above contention,
he placed reliance on the following cases:-
1.
Muhammad Umar versus Muqarab Khan and another (1968 SCMR 983) ;
2.
Mst Sahib Noor versus Haji Ahmad (1988 SCMR 1703) ;
3.
Ghulam Muhammad versus M. Ahmad Khan and 6 others (1993
SCMR 662) ; and
4.
Kunjabehari Chakrabarty versus Krishnadhone
Majumdar (AIR 1940 Calcutta 489).
With
regard to want/lack of jurisdiction as envisaged in Section 12(2) CPC,
it was submitted by Mr. Khalid Anwar that the making of an order by
a court in violation or in ignorance of any provision of law though
amounted to an illegality yet such an order could not be said to be
an order without jurisdiction or lacking in jurisdiction so as to bring
the same within the scope of the words “ want of jurisdiction”
and the same could not be challenged by an application under
Section 12(2) CPC but only by means of an appeal. In support of the
above, he placed reliance on the following cases:-
1.
Muhammad Khan and another versus Massan
and others (1999 SCMR 2464) ;
2.
Rehamt Ali versus The
Additional District Judge, Multan and others (1998 SCJ 761) ;
3.
Mst Naseem Akhtar and 4 others versus Shalimar General
Insurance Company Limited and 2 others (1994 SCMR 22) ;
4.
Muhammad Usman versus Pehlwan
and 4 others (2000 YLR 2324) ; and
5.
Saifuddin versus Zainuddin
and others (1992 MLD 631).
He
further submitted that in the circumstances, the order dated 18.2.98
was required to be challenged by way of an appeal under Section 21 of
the Banking Companies (Recovery of Loans, Advances, Credits and Finances)
Act, 1997 (hereinafter referred to as the Act of 1997) but the same
was not pressed into action and no appeal was filed against the above
order within thirty (30) days as provided in Section 21(1) of the Act
of 1997 on which the order attained finality and the appellants were
precluded from challenging the same by way of application under Section
12(2) CPC. In support of his above contention, he placed reliance on
the case of Mst Naseem Akhtar
and 4 others versus Shalimar General Insurance Company Limited and 2
others (1994 SCMR 22) (supra).
The arguments advanced by Mr. Khalid Anwar on the basis of which he had objected to the maintainability of these appeals are the same which were advanced by him while arguing the merits of the appeals. In the circumstances, it will be appropriate to proceed with the appeals on merits as the question of maintainability of the appeals being inter-linked with the objections and the grounds raised by Mr. Khalid Anwar would automatically decide the fate of the appeals with regard to their maintainability.
It
is without any dispute that the courts possess inherent power to set
aside their own judgment, decree or final order which had been obtained
fraudulently by way of misrepresentation and concealment/ suppression
of facts or collusively. This sub section provides an aggrieved person
with a right to file an application for recalling or setting aside a
decree, final order or judgment which had been obtained by fraud or
misrepresentation. The essential requirement for such an application
is that full particulars of the fraud and misrepresentation must be
given in the application. Fraud includes untrue statements by one who
did not believe it to be true and active concealment of facts. It is
also pertinent to note that the provisions of this section will not
be attracted when the alleged fraud or misrepresentation was not in
connection with the proceedings but prior their initiation. A party
alleging commission of fraud or misrepresentation in obtaining the decree,
judgment or final order has to state facts and circumstances which could
warrant a presumption or the possibility of commission of fraud or misrepresentation.
Mr. Sharifud-din- Pirzada has vehemently relied
on the case of Abdur Rehman
Khan versus Muhammad Altaf and 3 others
(1997 CLC 1260) wherein this Court pronounced that where allegation
of fraud was made during the course of judicial proceedings then it
was the duty of the court to investigate and inquire into the matter
to find out as to whether the impugned order or action was the result
of fraud or misrepresentation and without making a detailed inquiry
and investigation, the allegation of fraud ought not to have been rejected.
We are in agreement with the observations made by this Court in the
aforecited case. However, from a careful perusal of the aforecited case,
it transpires that it had been maintained that the allegation of fraud
or misrepresentation must be supported by the attending circumstances
and facts of the case and a presumption relating to the possibility
of commission of fraud should be forthcoming before any investigation
or inquiry could be ordered and on mere allegation without there being
any material to lend support or substantiate the commission of fraud
or making of misrepresentation would not require commencement of any
investigation or inquiry. This Court has further pronounced that there
ought to be specific and definite allegation of fraud. It will also
be pertinent to note that the definition of the fraud and the discussion
as to what amounted to fraud in the aforecited case would make it difficult
to infer that in the presence of the facts and circumstances of the
case it could be held that respondent NDFC had committed fraud as the
main ingredient of fraud namely, intention to deceive or to induce the
person by misrepresentation to enter into a contract on a false believe
would be found lacking inasmuch as the MOU did not contain any statement
which was in suppression of what was true or a representation of a false
fact. The action of respondent NDFC in including/adding the amount of
interest/mark up in the principal amount and then charging further interest
or mark up thereon was neither a misrepresentation nor a statement by
way of concealment or suppression of the true state of affairs in view
of the fact that the alleged illegal statements/ representations by
M/s NDFC were already within the knowledge of the appellant
Amongst the various essential grounds which a party is required to establish
for invoking the jurisdiction of a court under Section 12(2) CPC, one
essential ground is that the details of the alleged fraud, misrepresentation
or concealment should not have been within the knowledge of a party
who complains of fraud, misrepresentation or concealment during the
course of the proceedings. It is a well established principle of law
that where the facts on the basis of which the validity of the decree,
judgment or final order was questioned on the ground of fraud or misrepresentation,
an application under Section 12(2) CPC on the basis of such assertion
would not be sustainable if the same were within the knowledge of the
aggrieved party. The appellants’ case is that respondent NDFC committed
fraud, made misrepresentation and concealed facts by including/ adding
the amount of accrued interest/ mark up in the principal amount for
arriving at the principal amount which according to them was due and
payable as per statements made by them in the MOU and also charged further
mark up/ interest thereon in contradiction of the provisions of BCD's
Circulars No. 13 and 32. The above facts were within the knowledge of
the appellants. In the suit filed by the appellants against respondent
NDFC for redemption of the properties mortgaged as security for the
aforesaid loans/ advances/ finance facilities being suit No.416/98,
the appellants had categorically stated in para 5(xii) that pursuant
to the rescheduling agreement the defendant (respondent NDFC) had added
the interest, compound interest, additional interest and undue charges
in determining the principal amount due and payable and on this principal
amount a huge amount by way of mark up was also included. It will be
appropriate to reproduce para 5(xii) as under:-
“That the forced finance created by NDFC pursuant to Rescheduling Agreement/
Letters are on the fact of them extremely unconscionable bargins. In each of these forced loans, the interest, compound
interest, additional interest, undue charges have all been converted
into principal amount. On this principal amount, a huge amount by way
of mark up in price has been included. It is submitted that the Agreement/
Letter is so patently unreasonable and unconscionable that on this ground
alone these laons are liable to be struck down by this Hon’ble Court.
The Company is not liable to make any payments under these forced loans.
Thus the mode in which respondent NDFC had determined the principal amounts
as against the aforesaid various loans/ advances/ finance facilities
and charge of further mark up thereon as appearing in the Compromise
was already within the knowledge of the appellants and, therefore, such
statements and disclosures could not be said to be fraudulent or having
been made by way of misrepresentation as the appellants had the knowledge
of such facts. The appellants at no stage objected to the veracity and
correctness of such facts/ representations thereby implicitly accepting
them to be correct. Correspondingly, the mode of calculation of the
principal amount and determination thereof together with the stipulation
for charging further mark up could not be said to be fraudulent or by
way of concealment or suppression so as to amount to misrepresentation.
Mr. Sharifud-din-Pirzada
had referred us to the case of Government
of Sindh through the Chief Secretary and others versus Khalil Ahmed
and others (1994 SCMR 782) in support of his contention that
even a consent decree obtained on the ground of fraud could be challenged
where one of the parties to the agreement was made to agree upon the
terms and conditions of the contract by means of deceit. He had also
referred to the cases of (i) Union Carbide Corporation and others versus
Union of India and others (1991) 4 SCC 584 ; and (ii) Zafar Ahmad and 5 others versus Government
of Pakistan through Secretary, Ministry of Production, Islamabad and
6 others (1994 MLD 1612). These cases have been relied upon
by Mr. Sharifud-din-Pirzada on the ground that even an innocent representation
which was not correct would amount to misrepresentation and further
that a consent decree on the basis of an agreement suffering from fraud
or misrepresentation would also be liable to be challenged and set aside.
In support of his contention that a consent decree did not stand on
a higher footing or pedestal then ordinary decree and was amenable to
recall, setting aside or cancellation if the agreement or compromise,
terms and conditions of which were based on misrepresentation concealment
of facts and suffered from fraud, he placed reliance on the case of
Ruby Sales and services (P)
Ltd. and another versus State of Maharashtra
and others (1994) 1 SCC 531. We are in respectful agreement
with the pronouncement made in the aforecited cases and have no dispute
with the principle that even a consent decree is liable to be recalled,
set aside or cancelled if it could be proved that it was the result
of fraud or misrepresentation. However, in these appeals
the appellants have failed to bring on record material on the basis
of which it could be presumed or inferred that MOU contained misrepresentation,
suppression or concealment of facts, representations which were untrue
on the basis whereof wrong figure was allegedly calculated thereby causing
loss and injury to the appellants as they were made to make payments
of the sums/ amounts which they were not legally obliged to pay.
Mr. Khalid Anwar vehemently contended
that a party alleging fraud, misrepresentation, concealment/ suppression
of facts and wrong or illegal calculation was under a boundant duty to give the necessary particulars of the facts
which according to him amounted to fraud or misrepresentation. Mr. Khalid
Anwar further submitted that fraud cannot be said to have been committed
merely by the act of forgery or tendering a forged document in evidence
by one of the parties to proceeding as it did not amount to fraud on
court. In support of his above contention, he placed reliance on the
cases of (i) Muhammad Umar versus Muqarab
Khan and another (1968 SCMR 983) ; (ii) Central Bank of India, Ltd. versus Guardian Assurance Co., Ltd., and
another (AIR 1936 PC 179) ; and (iii) A.L.N. Narayanan Chettyar and another versus
Official Assignee, High Court Rangoon and another (AIR 1941 PC 93).
In all the
aforecited cases, it was held that where a party levels allegation of
fraud then it must specify and mention the details of the fraud and
further that the same was required to be proved beyond or reasonable
doubt and not on the basis of surmises, conjectures and suspicion. The
facts/ representations made by M/s NDFC in the MOU were neither
deceitful nor were based on misrepresentations as the appellants had
been informed of such facts/ statements which were to form the basis of
the Compromise prior to the making of the Compromise
The next ground urged by Mr. Sharifud-din-Pirzada was that the learned single Judge failed
to proceed in accordance with law as he was under an obligation to hold
an investigation and inquiry as to the commission of fraud or misrepresentation
again relying on the judgment of this Court in the case of Abdur Rehman Khan versus Muhammad Altaf and 3 others (1997
CLC 1260) (supra). He further submitted that the appellants’ application
under Section 12(2) CPC was challenged and controverted by means of
counter affidavit by respondent NDFC and the contents of the respondent’s
counter affidavit were controverted by way of affidavit in rejoinder
filed by the appellants and in such circumstances it was not possible
for the learned Single Judge to come to a definite and just conclusion
merely on the basis of the perusal of affidavit, counter affidavit,
and affidavit in rejoinder and it had become incumbent upon him to hold
investigation and inquiry by
framing issues and to call upon the party alleging fraud and misrepresentation
to produce evidence to substantiate the same. In support of his above
contention, he placed reliance on the cases of (i) Ghulam Muhammad versus M. Ahmad Khan and 6 others (1993 SCMR 662)
; and (ii) Abdul Razzaq
versus Muhammad Islam and 3 others (1999 SCMR 1714.
Mr. Khalid Anwar on the
other hand submitted that there was no principle or rule of law which
necessarily provided framing of issues and recording of evidence in
every case where allegation of fraud or misrepresentation
had been alleged and wherein the warring parties had filed counter affidavit
and affidavit in rejoinder and that the framing of the issues and calling
upon the parties to adduce evidence for decision thereon would be dependant
on the facts and circumstances of each case. In support of his above
contention, he referred us to the case of Abdul
Razzaq versus Muhammad Islam and 3 others
(1999 SCMR 1714) which had also been relied upon by Mr. Sharifud-din-Pirzada
in support of his contention that when the matter was contested before
the court it was incumbent upon the court to frame issues and record
evidence. Mr. Khalid Anwar had drawn our attention to page 1719 where
the court observed that it was necessary for the trial court to have
decided the application under Section 12(2) CPC after framing necessary
issues and allowing opportunity to the parties to lead evidence in support
of their respective pleadings but such framing of issues and recording
of evidence for contesting the application under Section 12(2) CPC was
dependant upon the facts and circumstances of each case. The
above observations relied upon by Mr. Khalid Anwar clearly support his
contention that it is not incumbent upon the trial court to lead evidence
and provide opportunity to the parties to lead evidence and such action
had to be resorted to on the basis of the facts and circumstances of
each case. We are unable to agree with the contention of Mr. Sharifud-din-Pirzada
that the order of learned Single Judge suffered from illegality on the
ground that he had neither framed issues nor provided an opportunity
to the appellants to establish their plea that the Compromise and the
decree suffered from fraud and misrepresentation, which has resulted
in miscarriage of justice and cause prejudiced to the appellants. The
facts of the case did not warrant framing of issues and providing an
opportunity to the parties to lead evidence. The authorities relied
upon by Mr. Sharifud-din-Pirzada, in the circumstances
and the facts of the case do not advance the case of the appellants
relating to holding investigation and inquiry into the question of fraud
and misrepresentation.
The consent decree dated
18.2.98 was challenged by Mr. Sharifud-din-Pirzada
on the ground of fraud, misrepresentation and being contrary to law
as it was against the categorical and specific provisions of BCD's Circulars
No.13 and 32 issued by State Bank of Pakistan prohibiting addition/inclusion
of the interest accrued on the principal amount as well as prohibiting
charging mark up or interest on such accrued interest or mark up. It
had been submitted that respondent NDFC was fully aware of the contents
of the aforesaid BCD's Circulars No. 13 and 32 but still in contravention
thereof, it made the appellants to pay mark up/ interest on mark up/
interest by including the accrued interest outstanding on the date of
the Compromise in the principal amount outstanding and then charging
further mark up/ interest thereon. In this connection, Mr. Khalid Anwar
had vehemently contended that the provisions o BCD's Circulars No.13
and 32 were not applicable to the case in hand as the loans/ finance
facilities had been granted to the appellants much earlier, i.e. sometime
in 1982 when there was no prohibition or bar from including/adding the
accrued interest in the principal and then charging interest/mark up
thereon. It was further submitted by him that the provisions of BCD's
Circulars No.13 and 32 were applicable to the loans/ advances granted
after 1st July, 1984. Mr. Khalid Anwar challenged the applicability
of BCD's Circulars No.13 and 32 on another ground and submitted that
at the time when the loans/ finance facilities in question were rescheduled
or restructured, M/s State Bank of Pakistan had issued two (2) further
Circulars bearing No.19 and 36 dated 5.6.97 and 17.7.97 respectively,
which were in the field and which contained the terms and conditions
on which outstanding loans/ finances/ advances were to be restructured
or rescheduled. It will be useful to reproduce paragraph 4(a) of BCD's
Circular No.19, which is as under:-
The details of the scheme are as under:-
(a)
All defaulters can make a full and final settlement of
their outstanding liabilities owing to a nationalised commercial bank/DFI
as under:-
|
|
Period of Default |
Repayment Terms |
|
i) |
7 years and
above |
Principal +
5% of Principal amount. |
|
ii) |
3 years or more
but less than 7 years. |
Principal +
20% of Principal amount. |
|
iii |
1 year or more
but less than 3 years. |
Principal +
40% of Principal amount or 75% of accrued mark up, whichever is
less. |
Mr. Khalid Anwar drew our attention to clause 3 of sub para (a)
of paragraph 4 to substantiate his contention that accrued mark up or
interest was recoverable along with the principal in cases of full and
final settlement of outstanding liabilities of a debtor. He also heavily
relied on BCD's Circulars No. 36 in support of his contention that respondent
NDFC was legally competent to include/ add the accrued interest/ mark
up on the principal amount loaned to the appellants and placed reliance
on paragraphs 2(A) (i) (ii) (iii) 2(B) and ‘C’ under the heading ‘Definition
of Principal’. It will also be advantageous to reproduce the aforesaid
provisions BCD's Circular No.36 as under:-
DEFINITION OF PRINCIPAL
(A)
Loans under Interest Based System:
The principal amount includes besides original amount
of advance, any or all of the following:
(i)
Subsequent enhancements therein.
(ii)
Disbursement made in excess over authorised limit and
(iii)
Other amounts payable by the customer including those
(NOT LEGIBLE) paid by the bank, such as SBP penalty, Excise Duty,
Exchange Risk Coverage Fees, debts for the use of credit cards and insurance
charges etc. In case of foreign currency loans, in the absence of any
exchange risk cover, the bank will apply the rate of exchange prevailing
on the date of payment by the bank to the lending agency/ foreign supplier.
(B) Finance under HIB System;
Under this system the purchase/ sale price will be the
amount payable/ recoverable on due dates alongwith all perforce payments
and may, therefore, be treated at par with the principal.
(C) Loans/Financing under Rescheduled/ Restructured
Arrangements:
In cases where rescheduling arrangements have been made,
the capitalised unpaid mark up and charges, if any, shall form part
of principal on the basis of rescheduling/ restructuring agreements.
If, however, the unpaid mark up has been capitalised without the legal
formalities/ documentation, it should not be recognised. In the cases
where capitalisation has been made with the proper documentation/ arrangements
sponsors/ lenders shall be free to negotiate and settle this issue amicably.
He finally contended that in view of the above provisions of
BCD's Circulars No. 19 and 36, the contention that respondent NDFC had
been guilty of fraud, misrepresentation and concealment as they illegally
included the amount of accrued mark up/ interest in the principal amount
for rescheduling/ restructuring the loan and again charging mark up/
interest thereon was against the provisions of BCD's Circulars No. 13
and 32 stood completely negated inasmuch as BCD's Circulars No. 13 and
32 stood modified by BCD's Circulars No. 19 and 36 which had issued
clarification regarding the definition of principal amount, wherein
they specifically allowed addition/ inclusion of mark up/ interest therein
and charging of further mark up and interest. The contention raised
by Mr. Khalid Anwar is not without substance and merits consideration.
The grievance of the appellants throughout had been that the respondent
had suppressed and concealed the facts and has also failed to abide
by the provisions of BCD's Circulars No. 13 and 32 which according to
them had the status of law and had bound respondent NDFC to observe
the same. This contention would have held ground if it could be established
that the provisions of BCD's Circulars No. 13 and 32 were applicable
with retrospective effect, that is to say that they were applicable
to the loans/ advances which had been granted earlier than 1st
July 1984. It may be pertinent to point out that w.e.f. 1st
July 1984, the Government had announced a policy according to which
it intended to bring to an end charging of interest/ Riba and had taken
certain measures to rid the economy of interest/ Riba. The aforesaid
two BCD's Circulars No. 13 and 32 were one of the several measures taken
by the Government to rid the country of interest/Riba. The wordings
of the aforesaid two Circulars are very clear and unambiguous and they
had been made effective from 1st July 1984. It is a settled
principle that Notifications, instructions, Circulars, etc. issued by
the Government or Statutory Bodies operate prospectively and not retrospectively.
In support of the above proposition, reliance is placed on the cases
: (i) Hashwani Hotels Limited versus Federation
of Pakistan and others reported in PLD 1997 SC 315; and (ii)
M/s Army Welfare Sugar Mills Ltd. and others
versus Federation of Pakistan and others reported in 1992 SCMR
1652. A perusal of the BCD's Circular No.13 of 1984 reveals that it
was the intention of the Government that the banking system should shift
over to Islamic modes of financing during the course of next financial
year and these modes of financing were described in clauses (i) (ii)
(iii) (iv) and (v) of paragraph 1. Paragraph 2 deleted the foreign loans
from operation/ instructions contained in sub paragraphs (i) (ii) and
(iii). A perusal of sub paragraph (i) of paragraph 1 reveals that during
the transitional arrangement/ period, the Banking Companies were given
a free hand to give loans/ advances on interest basis. In the circumstances,
the contentions of Mr. Sharifud-din Pirzada
that the contents of the Compromise were contrary to the provisions
of BCD's Circulars No. 13 and 32 relating to the inclusion/ addition
of the already accrued interest/ mark up in the principal amount for
the purpose of determining the principal amount due and payable by the
appellants and then charging further mark up/ interest thereon do not
hold ground in view of: firstly, that the provision thereof relating
to prohibition of inclusion/ addition of the accrued interest/ mark
up in the principal amount for determining the amount due and payable
was not applicable to the existing loans/ finance facilities, two of
which were admittedly foreign loans and were exempted from applicability
of the aforesaid Circulars; and secondly, that such an exercise i.e
inclusion/ addition of the mark up/ interest in the principal amount
for determining the amount due and payable by a debtor and charging
of mark up thereon was permissible by BCD's Circulars No. 19 and 36
which were in force at the time when rescheduling/ restructuring of
the loans/ finance facilities outstanding against the appellants was
undertaken. Respondent NDFC in the circumstances cannot be held responsible
for having made misrepresentation, concealment or suppression of facts
and making statements contrary to the Circulars having sanction of law.
In view of the above also the allegation of fraud, misrepresentation,
concealment and/ or suppression of facts and making statements contrary
to law is not established and accordingly the consent decree based on
MOU cannot be said to be suffering from any illegality as it was not
the result of fraud, misrepresentation or statements contrary to any
document having sanction of law and it could not have been challenged
on the ground of fraud and misrepresentation under Section 12(2) CPC.
The next ground on which Mr. Khalid Anwar assailed the appeals
was that even if it be presumed for the sake of arguments that the contents
of the Compromise, which was the basis of the consent decree were in
violation of the provisions of instructions/ Circulars having the force
of law, still the consent decree could not be challenged by way of an
application under Section 12(2) CPC as an order in contravention of
any provision of law could not be said to be an order passed for want
or lack of jurisdiction. He further submitted that an application under
Section 12(2) CPC could be made for recalling/ setting aside a decree,
judgment or a final order if it had been obtained from a court having
no jurisdiction to make the same and submitted that want of jurisdiction
could not be equated either with illegal or wrongful
exercise of jurisdiction by a forum having jurisdiction to decide
a particular matter. According to him, the learned Single Judge was
vested with jurisdiction to decide the matter and make a consent decree
and if an illegality was committed by him in violating any provision
of law in passing the consent order then such order could not be said
to be suffering from “want of jurisdiction” as envisaged in Section
12(2) CPC. It was further submitted by him that admittedly the Banking
Court while making the consent decree on the basis of the terms and
conditions embodied in the Compromise had the jurisdiction to proceed
with the matter and to pass a consent decree, therefore, it could not
be said to be a case of usurping or exercising jurisdiction not vesting
in the Banking Court. He had drawn our attention to the case of Ch.
Muhammad Ismail versus Fazal Zada, Civil Judge,
Lahore and 20 others PLD 1996 S.C. 246) in support of his contention
that misinterpreting the provisions of law and passing of an order in
contravention of the provisions by a forum having territorial and pecuniary
jurisdiction to decide the matter was not the same thing as wrong exercise
of jurisdiction and would not be a case of usurping jurisdiction but
would be a case of wrong exercise of jurisdiction and further that wrong
exercise of jurisdiction could not be equated with want of jurisdiction.
Consequently, he submitted that upon the above principle, the consent
decree was not the result of want of jurisdiction and the appellants
could not challenge the same by way of an application under Section
12(2) CPC inasmuch amongst others, one of the grounds on which such
a decree or a final order could be challenged was when the same had
been made for want of jurisdiction which was not the situation in the
present case. It was further submitted by Mr. Khalid Anwar that a decree
or final order passed in contravention of a provision of law was liable
to be challenged by way of an appeal and in support of his above contention
he placed reliance on the cases of (i) Bolan Bank Limited versus Capricorn Enterprise
(Pvt) Ltd.(1998 SCMR 1961); (ii) Muhammad
Khan and another versus Massan and others
(1999 SCMR 2464); and (iii) Rehamt Ali versus The Additional District Judge,
Multan and others (1998 SCJ 761.
Mr. Sharifud-din-Pirzada
in rebuttal of the arguments advanced by Mr. Khalid Anwar reiterated
the arguments which were advanced by him earlier while assailing the
order of the learned Single Judge, whereby he disposed of the J.Ms.
Petitions and the Misc. Applications in two Execution Applications and
submitted that MOU was an illegal document as it was based on misrepresentation;
contained statements which were untrue; that there was concealment or
suppression of facts which were within the knowledge of respondent NDFC
but the appellants had no knowledge thereof, which if had been within
the knowledge of the appellants, they would have never placed reliance
on MOU and would not have acted upon the same; and lastly that the contents/
representations made therein for repayment of the outstanding loans/finances
and for charging mark up thereon were absolutely in contravention of
the documents/ instructions which had force of law and a decree based
on such MOU was absolutely illegal, ultra virus and void ab initio and
was liable to be challenged under Section 12(2) CPC. He vehemently relied
on the case law which has already been reproduced herein above. The
case law relied upon by Mr. Sharifud-din-Pirzada is to the effect that when there was
a contest and the parties had filed counter affidavit and affidavit
in rejoinder then the matter required framing of issues and recording
of evidence for deciding the question as to whether fraud had been committed;
that a consent decree was liable to be challenged by an application
under Section 12(2) CPC when the same was obtained by fraud, misrepresentation
or for want of jurisdiction; that the consenting party was not precluded
from challenging the consent decree if it violated any of his legal
rights and he would not be deemed to have relinquished the same as there
was no estoppel against law; and that an order or decree in violation
of law could be challenged under Section 12(2) CPC. Regarding the pronouncement
that an order or decree in contravention of law could be challenged
by an application under Section 12(2) CPC, it may be pointed out that
the Indian Law on the issue is different from our law as in the Indian
CPC an order or decree in violation of any provision of a Statute be
attacked by means of an application analogous to Section 12(2) CPC.
The case law relied upon by Mr. Sharifud-din-Pirzada
is also of no assistance to the appellants as the question of fraud,
misrepresentation and or concealment of facts could not be established
on the basis of the facts and material on record which would preclude
the appellants from challenging the consent decree as it was specifically
asserted by Mr. Sharifud-din-Pirzada that
a consent decree could only be
challenged on the ground of fraud/ illegality.
It was further contended
by Mr. Khalid Anwar that in rescheduling/ restructuring an outstanding
loan for its repayment, provisions of BCD's Circulars were not to be
made applicable and submitted that in view of the above, the contention
that the provisions of BCD's Circulars No. 13 and 32 were not taken
into consideration while drafting the Compromise and passing of the
consent decree would not have any weight and the contention that the
Compromise was a fraudulent document having been obtained by misrepresentation,
suppression or concealment of facts and by statements contrary to law
would not be available to the appellants. In support of his contention,
he placed reliance on the case of United
Bank Limited versus Messrs Central Cotton Mills Ltd. and 5 others (2001
MLD 78).
We have gone through the
aforecited case which supports the contention of Mr. Khalid Anwar. However
this issue/ point has already been decided earlier while dealing with
the question of applicability of BCD's Circulars and holding that they
would be applicable prospectively and not retrospectively.
Mr. Sharifud-din-Pirzada
further contended that Circulars issued by the Banking Control Department
of State Bank of Pakistan were issued in exercise of the powers conferred
by Section 25 of the Banking Companies Ordinance, 1962 and that they
were in the nature of the instructions and or directives to the commercial
banks whether private or Government owned and they were under a boundant
duty to observe the such instructions/ Circulars. We do not disagree
with the contention advanced by Mr. Sharifud-din-Pirzada.
The fact, however, is that as has already been observed above, the BCD's
Circulars No. 13 and 32 relied by Mr. Sharifud-din-Pirzada
in support of his contention to establish that the Compromise and the
resultant consent decree was based on fraud, misrepresentation and violation
of statutory provisions have been found by us to be not applicable to
the restructuring or rescheduling of the loans/ finance facilities in
question as they had been granted much earlier to the date of the two
Circulars in question and the established principle that Notification
or orders, instructions issued by the executive authority of the Government
or a statutory body operate prospectively and not retrospectively. It
was further contended by Mr. Sharifud-din-Pirzada
that the aforesaid two Circulars also contained instruction/ directions
prohibiting charging/ levying interest and for shifting of other modes
of charging of interest as well as prohibiting the levy/ charge of mark
up on interest/ mark up which would be applicable to the case of the
appellants as respondent NDFC had in the Compromise demanded levy/ charge
of mark up on interest/ mark up which was not permissible in view of
the judgement dated 25.4.2001 in suit No.1659/99. This contention would
hold good but for our observation that the provisions of BCD's Circulars
No. 13 and 32 stood modified by subsequent BCD's Circulars No. 19 and
36 dated 5.6.1997 and 17.7.97 respectively which defined the principal
amount to include certain charges/ amounts/ expenses including the accrued
mark up/ interest.
After having considered
the merits of the case, the question of maintainability of the appeals
against order passed in J.Ms. No.29 and 30
will be taken up for consideration. The parties in dispute had compromised
and a compromise/ consent decree was passed on the basis of the Compromise.
This decree was acted upon by the appellants as they deposited four
quarterly instalments in pursuance of the consent decree towards the
repayment of the outstanding amount. Thereafter, default was committed
as the appellants did not deposit any further instalment as envisaged
by the consent decree. Mr. Khalid Anwar submitted that the appellants
could have challenged the consent decree by means of an appeal under
Order 43 Rule 1(m) CPC read with Section 21 of the Banking Companies
(Recovery of Loans, Advances, Credits and Finances) Act, 1997, if they
felt aggrieved but the said procedure not having been followed, after
expiry of the period of limitation provided in the aforesaid two provisions
of law the consent decree attained finality and could not be challenged
by the extra ordinary remedy provided by Section 12(2) CPC in the absence of proof that the same was obtained
by fraud or misrepresentation or the court making such decree had assumed
jurisdiction which did not vest in it. While considering the merits
of the appeal, we had come to the conclusion that neither the Compromise
nor the consent decree was based on fraud, misrepresentation and or
concealment of facts nor it was a case of want of jurisdiction as envisaged
in Section 12(2) CPC. In the circumstances, recourse to Section 12(2)
CPC was not permissible. In support of the above proposition, reliance
is placed on the cases of :-
1.
Mushtaq Ahmed and others versus Government of Pakistan
etc. (PLJ 1998 SC 866) ;
2.
Ch. Muhammad Ismail versus Fazal Dada, Civil Judge, Lahore
and 20 others (PLD 1996 SC 246) ;
3.
Municipal Committee versus Shaikh Aziz Illahi (PLD 1970 SC 506) ; and
4.
The Commissioner, Hyderabad Division versus Muhammad
and another (1969 SCMR 515).
In the first case, the Supreme Court refused to entertain a Constitutional
Petition on the ground that the aggrieved party had not availed of the
remedy of appeal available to him for challenging the impugned order.
The contention of the aggrieved party that the remedy by way of appeal
had become time barred was not found to be a ground for allowing the
aggrieved party to invoke the Constitutional jurisdiction of the Lahore
High Court and it was pronounced that he should have gone ahead with
challenging the impugned order in appeal with application seeking condonation
of delay on available grounds. In the second case, the aggrieved party
had filed a Constitutional Petition in the Lahore High Court to challenged
the order of rejection of plaint for non-payment of requisite court
fee. The Supreme Court observed that the order could have been assailed
by means of an appeal but the aggrieved party rushed to the High Court
with Constitutional Petition which course was held to be improper and
interference was declined. In the third case, a revision application
filed without exhausting the remedy of second appeal was held to be
incompetent. In the last case, invocation of writ jurisdiction by an
aggrieved party for challenging an order which could have been assailed
by a revision under Section 435 Cr.P.C. was held to be improper. In
the case in hand, the consent decree could have been challenged under
Order 43 Rule 1 clause (m) CPC as well as under Section 21 of the Banking
Companies (Recovery of Loans, Advances, Credits and Finances) Act, 1997
as the consent decree would be covered by the word “decree” used in
Section 21(1) of the Act of 1997. However, the appellants did not challenge
the consent decree. In view of the aforesaid provisions of law and on
the basis of the principle laid down by the Supreme Court in the aforecited
four (4) cases, they could not have validly invoke the jurisdiction
of the Banking Judge of this Court under Section 12(20 CPC especially
when they have failed to establish that the Compromise and the consequential
decree based thereon was the result of fraud, misrepresentation and/or
want of jurisdiction.
Mr. Khalid Anwar further submitted that the appellants were stopped
from challenging the consent decree as by not filing an appeal there
against and agreeing to act thereupon they had waived whatever right
they had to challenge the same. Mr. Sharifud-din-Pirzada vehemently controverted the arguments
advanced by Mr. Khalid Anwar and submitted that the question of estoppel
or waiver did not arise as there could be no estoppel against law and
in support of his above contention he placed reliance on the cases of
Pir Sabir Shah versus Shad Muhammad Khan, Member
Provincial Assembly, N.W.F.P. and another (PLD 1995 SC 66); and Malik Asad Ali and others versus Federation of Pakistan
through Secretary Law, Justice and Parliamentary Affairs Islamabad and
others (PLD 1998 SC 161.
Article 114 of the Qanun-e-Shahadat
Order deals with waiver or acquiescence and describes it as intentional
relinquishment of a known right or such conduct as would warrant an
inference of relinquishment of such right; implying consent to dispense
with or forgo something to which a person is entitled ; an agreement
to release or not to assert a right ; to constitute waiver there must
be some conscious giving up of a right and a person cannot be held bound
unless he is aware of what exactly he was waiving and what right he
was giving up with knowledge of all the facts. It has been observed
that where a person inspite of having full knowledge of violation of
any of his rights of personal nature remained silent and did not take
any measure for safeguarding it then he would be deemed to have impliedly
waived it. In the present case, in view of our observation that the
consent decree was not based on fraud or misrepresentation nor was obtained
in violation of any provisions of law, the right that was given up by
the appellants was their personal right of challenging the consent decree
as the appellants had not only remained quiet but also committed positive
acts by depositing four (4) quarterly instalments towards repayment
of the loan which was due and payable by them. However, a distinction
has to be made of waiver of rights created by law. The principle is
that a person has a right to waive the benefit of a law or rule made
solely for the benefit and protection of individuals in their private
capacity provided that such waiver does not result in any infringement
of any public right or public policy. In the case of Mrs Zehra Begum Messrs Pakistan Burmah-shell ltd. PLD 1984 SC 38), agreement by a
landlord to let out the premises for a fixed period was held to debar
him from seeking his ejectment on the ground of personal bona fide use
and occupation before the expiry of such fixed period. In the cited
case the landlord by agreeing not to eject the tenant before the expiry
of the fixed period had contracted against the provisions of the Sindh
Rented Premises Ordinance according to which he had the right to seek
ejectment of tenant on the ground of his personal use but the Supreme
Court repelled the objection raised on behalf of the landlord that placing
limitation on restriction for ejectment of the tenant for a particular
period amounted to violation of a law and the landlord could not waive
such right and it will be appropriate to reproduce the relevant passage
from the judgement as under:-
“In the
second place, even if there was such a right available under the law
(for arguments sake but not as a fact) it stood waived because it is
not a part of public policy, but of a personal privilege which the landlord
could forego for a valuable consideration.”
In the case of Yaqoob Ali versus
Ismail 1987 CLC 526), a learned Single Judge of this Court held
that where landlord had accepted rent fully knowing that default had
been committed but kept quiet for unreasonable period of time then he
would be deemed to have waived default. In the present case while entering
into the compromise, respondent NDFC had written off a sum about Rs.20
crores out of the principal amount due and payable in respect
of the outstanding loans/ advances. The learned Single Judge who accepted
the compromise and passed a decree thereon had applied his mind in decreeing
the suit on the basis of compromise and had disallowed a penal interest
of 4% which was agreed upon between the parties but only allowed the
mark up as agreed in the Compromise.
Mr. Sharifud-din-Pirzada
in rebuttal of the contention of waiver of right had placed reliance
on the cases of Pir Sabir
Shah versus Shad Muhamad, Malik Asad Ali &
others versus Federation of Pakistan and Union Carbide Corporation and
others versus Union of India and others (Supra). He had laid great emphasis
on the case of Union Carbide in support of his contention that an individual
could not be made to surrender/ relinquish a right conferred on him
by a Statute even by an order of the court or by being a party to a
consent order, whereby he had waived or surrendered any of his rights.
Mr. Sharifud-din- Pirzada had also placed
great emphasis on the pronouncements made by the Indian Supreme Court
in the above case of Union Carbide in support of his contention that
a right given by law to an individual for invoking the jurisdiction
of a court of law for redress of any wrong done to him or for enforcement
of any of his legal rights could not be taken away even by an order
of the court made with the consent of an individual. He also drew our
attention to the observations of the Indian Supreme Court that there
could be no estoppel of a provision of law relating to public policy
or public good and relying on the above cited case further submitted
that where there was no estoppel there could be no waiver. However,
the observations made in the cited case cannot be made applicable to
the facts and circumstances of the present case as in the cited case
relinquishment or waiver by individuals to forego their right to pursue
criminal prosecution was opposed to the provisions of the Indian Contract
Act, which provides that a person cannot enter into a contract, the
terms of which are opposed to a law or a public policy. The appellants
had neither relinquished or surrendered any of their rights relating
to invocation of jurisdiction of any court for redress of any grievance
as per orders of the court nor the right claimed by the respondents
to have been waived by the appellants was contrary to the provisions
of any law or was opposed to the public policy.
Mr. Sharifud-din-Pirzada vehemently criticised the impugned orders on the ground that the learned Single Judge did not take into consideration the provisions of the Corporate and Industrial Restructuring Ordinance, 2000 and Non-Performing Assets and Rehabilitation of Industrial Undertaking (Legal Proceedings) Ordinance. The provisions of CIRC Ordinance L of 2000 could not be pressed into by the appellants on the ground that the matter had been settled between the parties on 18.2.98 when the aforesaid Ordinances were not in the field. It was a past and closed transaction and the aforesaid two Ordinances did not provide any benefit to the outstanding loans/ advances/ finance facilities which had been disposed of by a competent court of law prior to coming into force of the said Ordinances.
With regard to the contention that an application jointly
under the provisions of the Non-Performing Assets and Rehabilitation
of Industrial Undertaking (Legal Proceedings) Ordinance and CIRC Ordinance
of 2000 was filed but was not properly considered and decided, it is
to be observed that the pendency of the application under Section 12(2)
CPC could not bring the case of the appellants within the purview o
Section 10 above as the application under Section 12(2) CPC was not
a valid and proper application in view of our observations herein above
that no case for resorting to Section 12(2) CPC was made out. In this
view of the matter, the appellants would not be able to take the benefit
of the above two Ordinances. Even otherwise, the two appeals against
the order on the applications under Section 12(2) CPC not being found
maintainable, the propriety of the order could not be examined.
For the foregoing reasons and discussion, we
have come to the conclusion that the appeals filed against the order
dismissing the application under Section 12(2) CPC were without any
substance as neither the Compromise nor the consent decree was based
on fraud and/or misrepresentation nor in making the consent orders/
decrees the learned Single Judge of this Court acting as Banking Court
assumed or usurped jurisdiction to make it a case of “want of jurisdiction”.
Consequently the consent orders/ decrees did not warrant to be assailed
under Section 12(2) CPC as the essential requirements necessary to invoke
the jurisdiction of a court under Section 12(2) CPC were missing. Similarly,
the two appeals against the order passed on CMA No.319 in Execution
Application No.110/2000 and CMA No.231/2001 in Execution Application
No.137/2000 are without any substance and do not merit consideration.
The appellants had filed applications under Section 151 CPC in both
the execution applications for staying the proceedings and also obtaining
orders that the proceedings therein were illegal as notice required
by Order 21 Rule 22(1)(a) was not served on the appellants and the requirement
being mandatory, violation thereof rendered the proceedings illegal
and liable to be set aside/ recalled. It is to be observed that both
the suits between the parties were disposed of by a consent order and
the decree was acted upon by the appellants by making payment of four
quarterly instalments. Execution Application was filed within one year
of the default. Even otherwise, in view of Rule 22(2) of Order 21 the
Court could issue a process in execution of a decree without issuing
notice for reasons to be recorded.
We are also satisfied
that both these appeals are not maintainable as the appellants had circumvented
the law by moving applications under Section 12(2) CPC which were not
legally maintainable for challenging the consent decrees in view of
the facts and circumstances of the case, i.e. failure of the appellants
to establish that the consent decree was obtained by fraud or misrepresentation
or that the same suffered for want of jurisdiction with a view to provide
them an opportunity to file the above High Court Appeals after obtaining
orders on such applications which appeals otherwise had become barred
by time.
Accordingly, all the four appeals stand dismissed in
limine.
CHIEF JUSTICE
Karachi:
Dated:19-09-2001. JUDGE

adabhoy judgment